Permit Clock

How long does a building permit take?

Real waits from application to issued permit for new housing, computed from each city's own permit records, not estimates. Calendar days, including the time applicants spend on corrections.

CityMedian daysMiddle halfSlowest tenthPermitsLatest issue date
Austin5627–1303362,340Oct 19, 2026
Los Angeles13873–2645447,987Oct 17, 2026
Seattle181130–2534891,148Oct 16, 2026

Trailing one-year window per city, ending at the latest issue date in each city's feed. "Slowest tenth" means one in ten permits waited at least that long.

In this window, a typical new-housing permit in Austin issued in 56 days; in Seattle it took 181 days.

By project type

Estimate when your permit will issue →

Planning a project? Contractor quote matching is coming soon. Permit Clock is independent and lists no contractors yet.