How long does a new-home permit take in Austin?

New single-family house permits (Austin permit class code 101). Window: issued Oct 20, 2025 to Oct 19, 2026.

Typical wait (median)50 days
Middle half of permits25–98days
Slowest one in ten wait at least223days
Permits measured2,045issued in the window

By ZIP code

ZIPMedian daysMiddle halfSlowest tenthPermits
787481413–4414035
786521515–181956
786172014–2549120
787472114–3978220
787582925–476225
787463427–9725331
786533521–5490107
787443624–56134374
787543627–5261124
787244826–7424439
787576244–9014691
787456846–175261128
787318044–12020554
787238541–10429672
787048768–152287127
787519366–17626925
787029462–146316117
7870311879–21127543
7875218285–27246827
78721207102–35836148
78741299116–36337532

ZIP codes with at least 25 permits in the window, fastest first.

Method.

Planning a project? Contractor quote matching is coming soon. Permit Clock is independent and lists no contractors yet.