How long do two-unit and secondary-apartment permits take in Austin?

New two-family buildings and secondary apartments (Austin permit class codes 102 and 103). Austin's backyard units and duplex-style second homes are filed under these classes. Window: issued Oct 20, 2025 to Oct 19, 2026.

Typical wait (median)127 days
Middle half of permits66–300days
Slowest one in ten wait at least361days
Permits measured167issued in the window

A new single-family home over the same window had a median of 50 days (details).

By ZIP code

ZIPMedian daysMiddle halfSlowest tenthPermits
787454832–12727850
78721361361–36457927

ZIP codes with at least 25 permits in the window, fastest first.

Austin's issued-permits feed only contains permits that were issued, so applications still under review are not counted. Method.