How long does an ADU or DADU permit take in Seattle?

New-construction permits whose dwelling-unit type includes an attached or detached accessory dwelling unit (AADU or DADU), with or without a new house.

Window: permits issued Jul 1, 2024 to Jun 30, 2025. That is the latest year in which Seattle's open data still records the dwelling-unit type; newer permits no longer carry it, so we can't tell which ones are ADUs.

Typical wait (median)180 days
Middle half of permits126–266days
Slowest one in ten wait at least480days
Permits measured506issued in the window

How this compares with the city's goals

SDCI's goal for pre-approved DADU plans is 30 days in City control; its reported 75th percentile is 60 days (SDCI permit performance, checked Oct 21, 2026). SDCI counts only days the application is with the City and notes the total wait an applicant experiences is roughly twice that. Our figure is the total calendar wait from application to issue, so it is longer.

All new housing permits in Seattle over the latest year: median 181 days (Seattle overview).

By ZIP code

ZIPMedian daysMiddle halfSlowest tenthPermits
98199148126–18721227
98103166113–21724239
98115170124–24446643
98117185138–28352257
98125189136–23940356
98133190128–23837534
98122277228–31356825
98118330170–75696354

ZIP codes with at least 25 permits in the window, fastest first.

Method.