How long does a building permit take in Seattle?

SDCI construction permits of type New that add at least one housing unit. Window: issued Oct 17, 2025 to Oct 16, 2026.

Typical wait (median)181 days
Middle half of permits130–253days
Slowest one in ten wait at least489days
Permits measured1,148issued in the window

By project type

Project typeMedian daysMiddle halfSlowest tenthPermits
All new housing permits181130–2534891,148

Seattle stopped recording the dwelling-unit type on recently issued permits, so the city table cannot split by home type for this window. See Seattle ADU permits for the latest period where the type is recorded.

ADU and DADU permits in Seattle

Is it getting faster?

Nov 2024: 253 days (n=51)Dec 2024: 189 days (n=77)Jan 2025: 218 days (n=66)Feb 2025: 203 days (n=69)Mar 2025: 189 days (n=79)Apr 2025: 219 days (n=92)May 2025: 194 days (n=82)Jun 2025: 182 days (n=70)Jul 2025: 196 days (n=95)Aug 2025: 211 days (n=93)Sep 2025: 246 days (n=50)Oct 2025: 178 days (n=87)Nov 2025: 198 days (n=64)Dec 2025: 162 days (n=100)Jan 2026: 158 days (n=86)Feb 2026: 166 days (n=66)Mar 2026: 169 days (n=143)Apr 2026: 178 days (n=128)May 2026: 173 days (n=80)Jun 2026: 196 days (n=92)Jul 2026: 190 days (n=106)Aug 2026: 190 days (n=98)Sep 2026: 183 days (n=90)Nov 2024Sep 2026
Median days from application to issue, by month issued (Nov 2024 to Sep 2026). Months with fewer than 25 permits are left out. Hover a bar for its value.

By ZIP code

ZIPMedian daysMiddle halfSlowest tenthPermits
98133152117–22636065
98199157113–18823445
98116161119–20421151
98103165127–221302125
98115165143–228309135
98117170134–246401102
98126171135–21423336
98105181130–41952259
98125181117–20924585
98106206187–33854634
98108208117–60965458
98177209172–30441928
98136217161–24327965
98118235162–48994889
98119273214–2921,03350

ZIP codes with at least 25 permits in the window, fastest first.

Source: Seattle Department of Construction and Inspections (SDCI), Building Permits (76t5-zqzr). 18 permits with impossible or extreme gaps were excluded. How we calculate this.