How long does a building permit take in Austin?
Permits for new residential buildings that add at least one housing unit (permit classes for single-family, secondary apartment, two-family, three-to-four and five-plus family). Window: issued Oct 20, 2025 to Oct 19, 2026.
Typical wait (median)56 days
Middle half of permits27–130days
Slowest one in ten wait at least336days
Permits measured2,340issued in the window
By project type
| Project type | Median days | Middle half | Slowest tenth | Permits |
|---|---|---|---|---|
| All new housing permits | 56 | 27–130 | 336 | 2,340 |
| New single-family homes | 50 | 25–98 | 223 | 2,045 |
| Two-unit homes and secondary apartments | 127 | 66–300 | 361 | 167 |
| Apartment buildings (3+ units) | 468 | 299–1,183 | 1,183 | 128 |
New single-family homes in Austin · Two-unit homes and secondary apartments
Is it getting faster?
By ZIP code
| ZIP | Median days | Middle half | Slowest tenth | Permits |
|---|---|---|---|---|
| 78748 | 14 | 13–44 | 140 | 35 |
| 78652 | 15 | 15–19 | 47 | 62 |
| 78617 | 20 | 14–25 | 49 | 121 |
| 78747 | 21 | 14–39 | 78 | 220 |
| 78653 | 35 | 21–54 | 90 | 107 |
| 78746 | 36 | 28–161 | 251 | 33 |
| 78754 | 36 | 27–52 | 61 | 124 |
| 78758 | 41 | 27–54 | 1,184 | 29 |
| 78744 | 42 | 24–71 | 284 | 414 |
| 78724 | 48 | 26–75 | 239 | 40 |
| 78745 | 59 | 42–176 | 275 | 179 |
| 78757 | 67 | 46–98 | 174 | 101 |
| 78731 | 82 | 48–122 | 204 | 59 |
| 78723 | 86 | 44–124 | 473 | 79 |
| 78751 | 89 | 66–160 | 260 | 29 |
| 78704 | 91 | 68–171 | 287 | 140 |
| 78702 | 93 | 66–145 | 316 | 124 |
| 78722 | 111 | 78–180 | 206 | 32 |
| 78703 | 112 | 78–206 | 300 | 65 |
| 78736 | 118 | 118–993 | 993 | 25 |
| 78752 | 179 | 64–204 | 433 | 33 |
| 78741 | 300 | 123–362 | 375 | 37 |
| 78721 | 358 | 146–361 | 364 | 75 |
| 78730 | 1,183 | 56–1,183 | 1,183 | 32 |
ZIP codes with at least 25 permits in the window, fastest first.
Source: City of Austin Development Services, Issued Construction Permits (3syk-w9eu). 27 permits with impossible or extreme gaps were excluded. How we calculate this.