How long does a building permit take in Austin?

Permits for new residential buildings that add at least one housing unit (permit classes for single-family, secondary apartment, two-family, three-to-four and five-plus family). Window: issued Oct 20, 2025 to Oct 19, 2026.

Typical wait (median)56 days
Middle half of permits27–130days
Slowest one in ten wait at least336days
Permits measured2,340issued in the window

By project type

Project typeMedian daysMiddle halfSlowest tenthPermits
All new housing permits5627–1303362,340
New single-family homes5025–982232,045
Two-unit homes and secondary apartments12766–300361167
Apartment buildings (3+ units)468299–1,1831,183128

New single-family homes in Austin · Two-unit homes and secondary apartments

Is it getting faster?

Nov 2024: 56 days (n=178)Dec 2024: 50 days (n=161)Jan 2025: 54 days (n=156)Feb 2025: 61 days (n=180)Mar 2025: 32 days (n=372)Apr 2025: 28 days (n=316)May 2025: 56 days (n=229)Jun 2025: 56 days (n=226)Jul 2025: 53 days (n=247)Aug 2025: 63 days (n=129)Sep 2025: 83 days (n=147)Oct 2025: 100 days (n=153)Nov 2025: 79 days (n=120)Dec 2025: 94 days (n=169)Jan 2026: 99 days (n=179)Feb 2026: 69 days (n=157)Mar 2026: 44 days (n=215)Apr 2026: 35 days (n=209)May 2026: 45 days (n=224)Jun 2026: 51 days (n=257)Jul 2026: 57 days (n=241)Aug 2026: 42 days (n=193)Sep 2026: 40 days (n=177)Nov 2024Sep 2026
Median days from application to issue, by month issued (Nov 2024 to Sep 2026). Months with fewer than 25 permits are left out. Hover a bar for its value.

By ZIP code

ZIPMedian daysMiddle halfSlowest tenthPermits
787481413–4414035
786521515–194762
786172014–2549121
787472114–3978220
786533521–5490107
787463628–16125133
787543627–5261124
787584127–541,18429
787444224–71284414
787244826–7523940
787455942–176275179
787576746–98174101
787318248–12220459
787238644–12447379
787518966–16026029
787049168–171287140
787029366–145316124
7872211178–18020632
7870311278–20630065
78736118118–99399325
7875217964–20443333
78741300123–36237537
78721358146–36136475
787301,18356–1,1831,18332

ZIP codes with at least 25 permits in the window, fastest first.

Source: City of Austin Development Services, Issued Construction Permits (3syk-w9eu). 27 permits with impossible or extreme gaps were excluded. How we calculate this.