Permit Clock
Permit Clock / Los Angeles

How long does a building permit take in Los Angeles?

LADBS permits with a net gain in dwelling units or ADUs, including new buildings, additions and conversions. Window: issued Oct 18, 2025 to Oct 17, 2026.

Typical wait (median)138 days
Middle half of permits73–264days
Slowest one in ten wait at least544days
Permits measured7,987issued in the window

By project type

Project typeMedian daysMiddle halfSlowest tenthPermits
All permits that add housing13873–2645447,987
New one- and two-family homes15197–2646231,995
New buildings that create an ADU16097–2825442,203
New apartment buildings771464–1,1481,260142

New ADU permits in Los Angeles

Is it getting faster?

Nov 2024: 170 days (n=604)Dec 2024: 154 days (n=602)Jan 2025: 160 days (n=666)Feb 2025: 170 days (n=688)Mar 2025: 166 days (n=735)Apr 2025: 145 days (n=719)May 2025: 126 days (n=708)Jun 2025: 129 days (n=635)Jul 2025: 130 days (n=707)Aug 2025: 114 days (n=731)Sep 2025: 124 days (n=692)Oct 2025: 114 days (n=728)Nov 2025: 127 days (n=604)Dec 2025: 125 days (n=689)Jan 2026: 132 days (n=646)Feb 2026: 158 days (n=692)Mar 2026: 147 days (n=719)Apr 2026: 148 days (n=675)May 2026: 147 days (n=697)Jun 2026: 135 days (n=654)Jul 2026: 143 days (n=649)Aug 2026: 139 days (n=591)Sep 2026: 133 days (n=683)Nov 2024Sep 2026
Median days from application to issue, by month issued (Nov 2024 to Sep 2026). Months with fewer than 25 permits are left out. Hover a bar for its value.

By ZIP code

ZIPMedian daysMiddle halfSlowest tenthPermits
913267335–22042833
913078542–12226288
913049241–213323112
913069242–182375140
913249456–16924370
913449449–189390191
913439852–190336139
913359952–193348238
914029944–16229973
9131110246–20226860
9104210552–318815101
9131610670–19568754
9134210656–192336153
9134510956–17537657
9140611161–189406139
9160511147–219547141
9006611277–197385159
9130311284–20842142
9027211375–1692281,177
9141111490–17568158
9133111759–200453202
9160712074–20031756
9142312164–21036465
9140512358–21931799
9132512476–19028494
9136712455–271435137
9003612791–22437949
9135212759–230513135
9135613165–21735480
9006413269–262491104
9003413678–32364384
9143613882–24856044
9160613875–238361125
9140113969–242686111
9002514275–23753264
9004514376–27639685
91403144125–18937440
9001614793–318709115
9006214889–29877858
9104015261–26280466
9001815489–31661865
9050115682–26853439
9160415692–27253866
9004315884–25144279
9004715988–29348785
9000316286–26054577
9136416379–33395069
9000416892–45496278
90038168101–49065841
9004416879–289543105
9004816890–22853442
9000216961–36348353
90024176113–41364631
9004117792–34269775
90031182118–8641,01039
90049182106–38668194
91601182117–472710105
9006518894–35974474
9003519186–31944868
9001119396–273405118
90019194102–318499120
90006196134–5401,15937
90037210154–33792781
91602219146–43778232
90027220117–52458056
90042227122–486718103
9006823094–48480236
90007234104–44373454
90023235156–35565529
90059241120–34557937
9003924888–7311,36993
90046251115–53999836
90291252119–41578372
90032264105–5881,07375
9002626698–6661,460100
90731268126–49780543
90008275138–49685751
90029284125–8051,02862
90710297112–37147225
90744324124–5031,09849
90033393112–56179036
90061621133–78291331

ZIP codes with at least 25 permits in the window, fastest first.

Source: Los Angeles Department of Building and Safety (LADBS), LADBS Building Permits Issued (pi9x-tg5x). 189 permits with impossible or extreme gaps were excluded. How we calculate this.

Planning a project? Contractor quote matching is coming soon. Permit Clock is independent and lists no contractors yet.