How long does an ADU permit take in Los Angeles?

New-building permits where LADBS records at least one accessory dwelling unit (the adu_changed field). Garage conversions and other ADU alterations are not separable in this feed and are excluded. Window: issued Oct 18, 2025 to Oct 17, 2026.

Typical wait (median)160 days
Middle half of permits97–282days
Slowest one in ten wait at least544days
Permits measured2,203issued in the window

For comparison, all new one- and two-family home permits in Los Angeles had a median of 151 days over the same window (1,995 permits).

ADU wait by ZIP code

ZIPMedian daysMiddle halfSlowest tenthPermits
9006610475–13920940
9104211758–42183135
9134311763–18926539
9130411870–29244036
9027212281–176233231
91325132102–19032629
9006413472–24833627
9134413486–23747358
9140613676–31146350
9160513877–21259736
91606140106–23026534
91405142123–23731732
9130614580–24941540
9133114589–25759853
9133514694–27634866
9134215191–24248049
91401151104–22144234
9004415870–28649030
91356166122–25336632
9135216882–25851846
90049180121–29062236
91367191101–27847744
90016207127–38876933
90011209133–29353359
90037212185–35760926
91601224159–47270834
90032241109–42458831
90019249173–41954325
90042281175–51779042
90039432110–73886927

ZIP codes with at least 25 permits in the window, fastest first.

Counted from application (LADBS submitted date) to issue date, in calendar days, so the figure includes time spent on plan-check corrections. Method.

Planning a project? Contractor quote matching is coming soon. Permit Clock is independent and lists no contractors yet.