Permit Clock / Los Angeles / ADU permits
How long does an ADU permit take in Los Angeles?
New-building permits where LADBS records at least one accessory dwelling unit (the adu_changed field). Garage conversions and other ADU alterations are not separable in this feed and are excluded. Window: issued Oct 18, 2025 to Oct 17, 2026.
Typical wait (median)160 days
Middle half of permits97–282days
Slowest one in ten wait at least544days
Permits measured2,203issued in the window
For comparison, all new one- and two-family home permits in Los Angeles had a median of 151 days over the same window (1,995 permits).
ADU wait by ZIP code
| ZIP | Median days | Middle half | Slowest tenth | Permits |
|---|---|---|---|---|
| 90066 | 104 | 75–139 | 209 | 40 |
| 91042 | 117 | 58–421 | 831 | 35 |
| 91343 | 117 | 63–189 | 265 | 39 |
| 91304 | 118 | 70–292 | 440 | 36 |
| 90272 | 122 | 81–176 | 233 | 231 |
| 91325 | 132 | 102–190 | 326 | 29 |
| 90064 | 134 | 72–248 | 336 | 27 |
| 91344 | 134 | 86–237 | 473 | 58 |
| 91406 | 136 | 76–311 | 463 | 50 |
| 91605 | 138 | 77–212 | 597 | 36 |
| 91606 | 140 | 106–230 | 265 | 34 |
| 91405 | 142 | 123–237 | 317 | 32 |
| 91306 | 145 | 80–249 | 415 | 40 |
| 91331 | 145 | 89–257 | 598 | 53 |
| 91335 | 146 | 94–276 | 348 | 66 |
| 91342 | 151 | 91–242 | 480 | 49 |
| 91401 | 151 | 104–221 | 442 | 34 |
| 90044 | 158 | 70–286 | 490 | 30 |
| 91356 | 166 | 122–253 | 366 | 32 |
| 91352 | 168 | 82–258 | 518 | 46 |
| 90049 | 180 | 121–290 | 622 | 36 |
| 91367 | 191 | 101–278 | 477 | 44 |
| 90016 | 207 | 127–388 | 769 | 33 |
| 90011 | 209 | 133–293 | 533 | 59 |
| 90037 | 212 | 185–357 | 609 | 26 |
| 91601 | 224 | 159–472 | 708 | 34 |
| 90032 | 241 | 109–424 | 588 | 31 |
| 90019 | 249 | 173–419 | 543 | 25 |
| 90042 | 281 | 175–517 | 790 | 42 |
| 90039 | 432 | 110–738 | 869 | 27 |
ZIP codes with at least 25 permits in the window, fastest first.
Counted from application (LADBS submitted date) to issue date, in calendar days, so the figure includes time spent on plan-check corrections. Method.
Planning a project? Contractor quote matching is coming soon. Permit Clock is independent and lists no contractors yet.